Project Management Professional (PMP) — Question 1252

A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.
Which two documents should the project manager update as soon as possible? (Choose two.)

Answer options

Correct answer: A, D

Explanation

The Issue log should be updated to reflect the discovered invoice errors, documenting the issues that arose during the project. The Change log should also be updated to track any changes made in response to these issues. The Risk register, Stakeholder register, and Backlog register are not directly related to the immediate resolution of the invoicing errors.