Project Management Professional (PMP) — Question 1253
During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible.
What approach should be used in this situation?
Answer options
- A. The team facilitator gets support from external team members.
- B. The team members bring in a specialist to help them
- C. The product owner moves it to the product backlog.
- D. The cross-functional team member work together to complete the activity
Correct answer: D
Explanation
The correct answer is D because having cross-functional team members work together ensures that various skills and expertise are utilized to address the complexity and expedite the completion of the task. Options A and B involve external assistance which may slow down the process, while option C delays the task by moving it to the backlog instead of addressing the issue immediately.