A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards.
What should the project manager do?
Answer options
- A. Ask the senior manager to approve the user acceptance testing (UAT) plan
- B. Inform the senior manager that there are approved quality standards
- C. Review the quality management plan with the senior manager
- D. Estimate the backlog items to forecast quality
Correct answer: C
Explanation
The correct answer is C because reviewing the quality management plan with the senior manager addresses their concerns directly and ensures alignment on quality expectations. Option A does not resolve the manager's concerns, while B simply states existing standards without engaging in a discussion. Option D focuses on estimating backlog items rather than addressing the immediate quality concerns.