Project Management Professional (PMP) — Question 1195

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule. The project team also has concerns about the impact of scope changes on the project schedule.
What should the project manager do to keep the project on schedule while still meeting project objectives?

Answer options

Correct answer: A

Explanation

The correct answer is A because collaborating with the CCB allows for a thorough review of scope changes, ensuring that any adjustments align with the project's goals. Option B is not ideal as simply submitting a change request without collaboration may overlook important impacts. Options C and D do not address the need for formal scope approval and could lead to further scheduling issues.