Project Management Professional (PMP) — Question 1175

Project reviews are done regularly in a project. The team has encountered a critical technical issue that will be discussed in the next project review.
Who should the project manager invite to the review for an effective decision on the way forward?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the project team is directly involved with the technical aspects of the project and is best equipped to discuss the critical issue. While the internal, management, and end user teams may offer valuable input, they do not have the same level of technical knowledge and direct involvement as the project team.