Project Management Professional (PMP) — Question 1105
A key stakeholder who is frustrated by the lack of transparency of IT projects declines an invitation to participate in the new project meetings. What should the agile project manager do to engage the stakeholder in the project?
Answer options
- A. Introduce the stakeholder to the project team and invite them to the next iteration review meeting with the IT team.
- B. Use stakeholder mapping to document the level of influence and interest for the next iteration planning meeting.
- C. Present the project management plan to the stakeholder and reassure them that they will receive regular project updates.
- D. Build trust with the stakeholder by keeping project commitments and use demo sessions to gather feedback and realign goals.
Correct answer: D
Explanation
The correct answer, D, focuses on building trust and engagement through commitment and feedback, which addresses the stakeholder's frustration. Options A and B do not directly alleviate the stakeholder's concerns or involve them meaningfully, while option C may reassure them but fails to actively engage and rebuild trust.