Project Management Professional (PMP) — Question 1104
A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?
Answer options
- A. Projects with the least associated risks
- B. Projects with maximum revenue generation
- C. Projects with the least duration
- D. Projects that maximize the business value
Correct answer: D
Explanation
The correct answer is D because maximizing business value ensures that the selected projects align with the overall strategic goals and deliver the highest impact. Options A, B, and C focus on specific aspects like risks, revenue, or duration, which do not necessarily guarantee the project's contribution to the organization's long-term success.