Project Management Professional (PMP) — Question 1103

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile practices, which are relevant to the project.

What should the project manager do to gain buy-in from the different stakeholders?

Answer options

Correct answer: B

Explanation

The correct answer is B because organizing a meeting allows for direct communication and engagement with stakeholders, helping them understand the benefits of agile practices. Option A lacks interaction and may not effectively address stakeholder concerns. Option C delegates the responsibility to the PMO, which may not be effective in gaining buy-in. Option D focuses on training rather than building initial support and understanding among stakeholders.