Project Management Professional (PMP) — Question 11

A new law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because assessing and prioritizing the impact of the new law is essential for informed decision-making regarding the project's direction. Option A may not be necessary without first understanding the full impact, while B could lead to reduced project quality. Option C, although important, does not directly address the immediate effects on the project plan.