A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version is not clear to the stakeholders.
What should the project manager do to increase value delivery?

Answer options

Correct answer: C

Explanation

The correct answer is C because defining a minimum viable product (MVP) helps clarify the vision and ensures that stakeholders have a concrete understanding of what the digital version will entail. Options A and B do not directly address the stakeholders' lack of clarity about the vision, and option D focuses on technical risks rather than enhancing stakeholder understanding and value delivery.