Project Management Professional (PMP) — Question 103

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

Answer options

Correct answer: C

Explanation

The correct answer is C because ensuring that the reports align with the communications management plan is vital for effective stakeholder communication. Option A does not address the stakeholder's concerns, while B may be premature without first understanding the specific inadequacies. Option D shifts responsibility away from the project manager, which is not advisable in this scenario.