Project Management Professional (PMP) — Question 102

A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

Answer options

Correct answer: C

Explanation

The correct answer is C because evaluating the nature of the request allows the project manager to understand its implications and communicate effectively with stakeholders. Options A and B focus on resource allocation and budgeting, which may not be necessary if the request is not warranted. Option D suggests a formal process that might not be needed for a simple operational task.