Project Management Professional (PMP) — Question 1021
An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.
What should the servant leader do?
Answer options
- A. Remove the certification need from the project scope.
- B. Escalate this to the project director for a resolution.
- C. Review the process and remove the impediment.
- D. Escalate this to the agile lead of the second team.
Correct answer: C
Explanation
The correct answer is C because the servant leader should focus on identifying and removing any obstacles that prevent the second team from certifying the deliverable. Options A and B do not address the underlying issue, while D does not provide a direct solution to the delay.