PMI Scheduling Professional (PMI-SP) — Question 45
Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?
Answer options
- A. Records Management System
- B. Performance reporting
- C. Inspection and Audit
- D. Payment System
Correct answer: A
Explanation
The correct answer is A, Records Management System, as it is specifically designed to manage and organize contracts and procurement documents. The other options, while relevant in different contexts, do not focus on the management of documentation and records related to procurements.