PMI Scheduling Professional (PMI-SP) — Question 44
You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?
Answer options
- A. Expert Judgment
- B. Decomposition
- C. Rolling Wave Planning
- D. Templates
Correct answer: D
Explanation
Templates provide established formats and structures that can help identify typical schedule milestones effectively. While Expert Judgment, Decomposition, and Rolling Wave Planning are valuable techniques, they do not focus specifically on identifying standard milestones to the same extent as templates do.