PMI Scheduling Professional (PMI-SP) — Question 43

The Define Activities process is the first process in the project time management knowledge area. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

Answer options

Correct answer: D

Explanation

The correct answer is D, as 'Project document updates' is not a direct output of the Define Activities process. The other options, including the Activity list, Milestone list, and Activity attributes, are all specific outputs that result from the activities defined in this process.