PMI Scheduling Professional (PMI-SP) — Question 42
Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and distribute information to the stakeholders about the project costs, schedule, and performance. What term is assigned to this communication tool?
Answer options
- A. Project management information system
- B. Table reporting
- C. Reporting system
- D. Communications management system
Correct answer: C
Explanation
The correct answer is 'C. Reporting system' because it specifically refers to tools designed for capturing and conveying project-related information. While 'A. Project management information system' and 'D. Communications management system' are related concepts, they encompass broader functionalities beyond just reporting. 'B. Table reporting' is not a standard term used to describe a comprehensive communication tool in project management.