PMI Scheduling Professional (PMI-SP) — Question 41
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?
Answer options
- A. Estimate activity durations
- B. Estimate activity resources
- C. Control schedule
- D. Develop schedule
Correct answer: C
Explanation
The correct answer is C, Control schedule, as you are actively managing and adjusting the project timeline due to delays. Options A and B pertain to estimating durations and resources before the project execution rather than adjusting after issues arise. Option D, Develop schedule, focuses on the initial creation of the schedule, not the revision of an existing one.