PMI Scheduling Professional (PMI-SP) — Question 46

In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?

Answer options

Correct answer: C

Explanation

The correct answer is C, Control schedule, as it involves monitoring and managing the project schedule, which typically demands continuous attention and effort throughout the project lifecycle. The other options, while important, either focus on initial planning (A and B) or on establishing the schedule (D), which do not require as much ongoing effort as controlling the schedule.