PMI Scheduling Professional (PMI-SP) — Question 27

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

Answer options

Correct answer: C

Explanation

The correct answer is C, as the Precedence diagramming method is primarily used for scheduling tasks rather than defining them. In contrast, Decomposition, Rolling wave planning, and Templates are all effective techniques for breaking down and defining project activities.