PMI Scheduling Professional (PMI-SP) — Question 26

Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

Answer options

Correct answer: A, C, D

Explanation

The correct answers are A, C, and D, as these are all outputs of the Determine Budget process. Option B, the Scope baseline, is not an output of this process; it is developed during the Create WBS process.