PMI Scheduling Professional (PMI-SP) — Question 24
You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen delays that will require your attention. You will need four inputs to the control schedule process. Which of the following documents would not be an input for the control schedule process?
Answer options
- A. Project schedule
- B. Work performance information
- C. Project management plan
- D. Earned value management results
Correct answer: D
Explanation
The correct answer is D because earned value management results are not directly used as inputs for controlling the schedule; rather, they are used for performance measurement. In contrast, the project schedule, work performance information, and project management plan are essential inputs for the control schedule process as they provide the necessary context and data for making adjustments.