PMI Scheduling Professional (PMI-SP) — Question 23

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

Answer options

Correct answer: C

Explanation

The estimate at completion (EAC) is calculated based on the current progress and costs incurred. Given the budget and current spending, option C, $441,025.64, reflects the projected cost to complete the project, while the other options do not align with the calculations of EAC based on the provided data.