PMI Scheduling Professional (PMI-SP) — Question 28
You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequencing of the project activities, you will need a document to identify the result of project phases, key project deliverables, and significant, timeless events in the project. Which of the following documents will you need to help sequence the project work?
Answer options
- A. Activity attributes
- B. Activity list
- C. Project scope statement
- D. Milestone list
Correct answer: D
Explanation
The Milestone list is the correct choice as it highlights significant events and key deliverables, aiding in the sequencing of activities. While the Activity attributes and Activity list provide details about tasks, they do not focus specifically on key milestones necessary for sequencing. The Project scope statement defines the project boundaries but does not detail the timing of project events.