PMI Risk Management Professional (PMI-RMP) — Question 198
The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only. Where would the project manager find the list of recipients for the report?
Answer options
- A. Communications management plan
- B. Risk management plan
- C. Risk register
- D. Project charter
Correct answer: A
Explanation
The communications management plan outlines how information is shared within a project, including who will receive specific reports. The risk management plan focuses on identifying and managing risks, while the risk register contains details about risks, and the project charter provides an overview of the project but does not specify report recipients.