PMI Risk Management Professional (PMI-RMP) — Question 197
The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?
Answer options
- A. Work breakdown structure
- B. Risk breakdown structure
- C. Critical path method
- D. Organizational breakdown structure
Correct answer: A
Explanation
The Work breakdown structure (WBS) is essential for schedule metrics as it breaks down the project into manageable sections, allowing for accurate tracking of progress and timelines. The Risk breakdown structure, Critical path method, and Organizational breakdown structure do not directly provide the necessary inputs for measuring schedule metrics.