The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database.
A ) Effectiveness of risk response
B ) Unexpected or undocumented risks which occur
C ) Relevant risk data -
D ) Management reserve report -
Which of the following should be included?
Answer options
- A. A, B, C
- B. A, C, D
- C. B, C, D
- D. A, B, D
Correct answer: A
Explanation
The correct answer A includes the effectiveness of risk response, unexpected risks, and relevant risk data, all of which are crucial for learning from past experiences. Options B, C, and D exclude one or more of these important elements, making them incomplete for the lessons learned database.