PMI Risk Management Professional (PMI-RMP) — Question 199

The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database.
A ) Effectiveness of risk response
B ) Unexpected or undocumented risks which occur

C ) Relevant risk data -

D ) Management reserve report -
Which of the following should be included?

Answer options

Correct answer: A

Explanation

The correct answer A includes the effectiveness of risk response, unexpected risks, and relevant risk data, all of which are crucial for learning from past experiences. Options B, C, and D exclude one or more of these important elements, making them incomplete for the lessons learned database.