PMI Risk Management Professional (PMI-RMP) — Question 126
The project manager of a project in trouble actively participates in a project risk assessment. After the assessment is complete, the project manager receives the final results.
What is the best recommended action to be taken from this point onward?
Answer options
- A. Schedule a meeting and present the assessment results.
- B. Use the assessment results in the day-to-day management of project risks.
- C. Schedule a meeting with the project sponsor and discuss the assessment results.
- D. Use the assessment results to review the project hand over plan to operations.
Correct answer: B
Explanation
The correct action is to use the assessment results in the day-to-day management of project risks, as this ensures proactive handling of identified risks. While scheduling meetings to discuss results (options A and C) is useful, it does not directly address the ongoing management of risks. Option D, reviewing the project hand over plan, is less immediate compared to integrating risk management into daily operations.