PMI Risk Management Professional (PMI-RMP) — Question 125
Most risks are assessed for probability and impact. Which of the following are other factors that should be considered?
Answer options
- A. Urgency and complexity
- B. Manageability and cost
- C. Urgency and manageability
- D. Manageability and complexity
Correct answer: C
Explanation
The correct answer is C because urgency and manageability are critical in determining how quickly a risk needs to be addressed and how feasible it is to manage that risk. Options A, B, and D, while relevant, do not capture the same essential dynamic of prioritizing risk response based on urgency and the ability to manage the risk effectively.