PMI Risk Management Professional (PMI-RMP) — Question 128
The risk manager wants to determine what is to be measured, how it is to be measured, and what project outcomes are to be measured. In which of the following processes should this be established?
Answer options
- A. Initiating Process
- B. Executing Process
- C. Planning Process
- D. Monitoring and Controlling Process
Correct answer: C
Explanation
The correct answer is C, as the Planning Process involves defining the metrics and outcomes to be measured for a project. The Initiating Process focuses on project authorization, the Executing Process is about carrying out the project plans, and the Monitoring and Controlling Process is concerned with tracking progress rather than establishing measurement criteria.