PMI Professional in Business Analysis (PMI-PBA) — Question 91
The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?
Answer options
- A. Use cases
- B. Project scope
- C. Delphi outcome
- D. RACI chart
Correct answer: A
Explanation
Use cases provide detailed scenarios that describe how users will interact with the system, which directly relate to acceptance criteria. The project scope outlines the overall goals and deliverables but does not detail user interactions. The Delphi outcome is more about consensus and not specifically about acceptance criteria. A RACI chart identifies roles and responsibilities but does not define how project success is measured.