PMI Professional in Business Analysis (PMI-PBA) — Question 41
When a business analyst uses subject matter experts to define roles and identify influencers, which project artifact is created or updated?
Answer options
- A. Stakeholder management plan
- B. RACI matrix
- C. Stakeholder register
- D. SWOT analysis
Correct answer: C
Explanation
The correct answer is C, the Stakeholder register, as it is specifically used to document stakeholders' roles and their influence on a project. The Stakeholder management plan focuses on how to engage with stakeholders, the RACI matrix defines responsibilities, and the SWOT analysis assesses strengths, weaknesses, opportunities, and threats, none of which directly concern the identification of roles and influencers.