PMI Professional in Business Analysis (PMI-PBA) — Question 42

The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?

Answer options

Correct answer: B

Explanation

The correct answer is B because conducting inspections allows the business analyst to proactively identify gaps in requirements and make necessary adjustments to the baseline. Options A and C focus on documentation and meetings, which are important but do not directly address the ongoing evaluation of requirements. Option D is about risk management rather than tracking requirements themselves.