PMI Professional in Business Analysis (PMI-PBA) — Question 28

What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?

Answer options

Correct answer: C

Explanation

The correct answer is C because validating requirements that stakeholders prioritize ensures that the most critical needs are addressed before development. Options A and B do not focus on quality validation, while option D is about testing approval, which is not directly related to ensuring requirement quality.