PMI Professional in Business Analysis (PMI-PBA) — Question 26
The business analyst wants to ensure that requirement changes can be formally tracked after the product is baselined. What will the business analyst need to evaluate the proposed change?
Answer options
- A. Scope statement
- B. Impact analysis
- C. Requirements management plan
- D. Pareto analysis
Correct answer: B
Explanation
The correct answer is B, Impact analysis, as it allows the business analyst to evaluate the effects of proposed changes on the project. The other options, such as the Scope statement and Requirements management plan, are important documents but do not specifically focus on assessing the implications of changes. Pareto analysis is a technique used for prioritization, not for tracking requirement changes.