PMI Professional in Business Analysis (PMI-PBA) — Question 29

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.
What could have caused this?

Answer options

Correct answer: C

Explanation

The correct answer is C because if requirement changes are not documented in the project charter, it can lead to misunderstandings about what the client expects. Option A is incorrect because while a requirements matrix is important, the failure to track client requirements does not directly relate to the project's charter. Options B and D are also not correct as they pertain to the design review and testing adequacy, which may not directly address the client’s specification agreement.