PMI Professional in Business Analysis (PMI-PBA) — Question 14
A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
Answer options
- A. Sequence diagram
- B. Requirements traceability matrix
- C. Requirements attributes table
- D. Project schedule and cost baseline
Correct answer: B
Explanation
The Requirements traceability matrix is essential for assessing the implications of changes, as it links requirements to their corresponding features. The other options, such as the Sequence diagram, Requirements attributes table, and Project schedule and cost baseline, do not specifically track changes or modifications related to existing requirements.