PMI Professional in Business Analysis (PMI-PBA) — Question 13

Requirements elicitation for a project is occurring. The marketing, acquisition, and production departments want to include specific requirements. The CEO has a requirement to deploy in three months.
Which of the following actions will have a greater influence on the project success?

Answer options

Correct answer: C

Explanation

The correct answer is C because conducting a stakeholder analysis helps in understanding the influence and interests of various parties involved, which is crucial for balancing competing requirements. Options A and B may overlook the importance of stakeholder influence, potentially leading to misalignment with project goals. Option D could be impractical as it relies on gaining an extension, which might not be feasible.