PMI Agile Certified Practitioner (PMI-ACP) — Question 94
An agile team is working well together, but productivity has been flat.
What can the project leader do to help them improve performance?
Answer options
- A. Review the burndown chart to identify ways to increase efficiency
- B. Chair a weekly team retrospective focusing on identifying areas for continuous improvement
- C. Ask a senior manager to initiate a root-cause analysis
- D. Identify team key performance indicators (KPIs) and create positive incentives when targets are achieved
Correct answer: B
Explanation
The correct answer is B because conducting regular retrospectives allows the team to reflect on their processes and identify specific areas for enhancement. Options A and C focus on analysis rather than team-driven improvement, while option D, although beneficial, does not directly address the need for immediate reflection and adaptation in team practices.