An agile practitioner becomes a Scrum Master on an established Scrum team.
After introductions, what should the agile practitioner do?

Answer options

Correct answer: B

Explanation

The correct answer is B because the Scrum Master should first assess the team's adherence to Scrum practices to ensure they are following the framework correctly. Options A, C, and D are more focused on team development and backlog management, which are important but should come after addressing process alignment.