PMI Agile Certified Practitioner (PMI-ACP) — Question 95
Business stakeholders of an agile project frequently skip the review meetings.
What should the agile practitioner do?
Answer options
- A. Ask the product owner to inform all stakeholders about the project's progress
- B. Send meeting notes to all stakeholders after each review meeting
- C. Include the results of the review meetings in the information radiators
- D. Convince the stakeholders of the benefits of attending the review meetings
Correct answer: D
Explanation
The correct answer is D because convincing stakeholders of the benefits encourages their participation, which is crucial for project success. The other options, while helpful, do not directly address the issue of stakeholder engagement in the review meetings.