PMI Agile Certified Practitioner (PMI-ACP) — Question 81
How should an agile project leader interact with the product owner?
Answer options
- A. Conduct regular one-on-one meetings to review development features and trace them back to the product roadmap
- B. Ensure the they attend regular sprint meetings to provide product-feature feedback
- C. Share any new versions of the project plan with them, including updated statuses for tasks and project milestones
- D. Schedule meetings where they can provide team direction regarding new-feature priorities and upcoming sprints
Correct answer: B
Explanation
The correct answer is B because regular sprint meetings allow the product owner to give immediate feedback on product features, ensuring alignment with project goals. Options A, C, and D, while beneficial, do not provide the same level of ongoing interaction and timely feedback that sprint meetings facilitate.