PMI Agile Certified Practitioner (PMI-ACP) — Question 81

How should an agile project leader interact with the product owner?

Answer options

Correct answer: B

Explanation

The correct answer is B because regular sprint meetings allow the product owner to give immediate feedback on product features, ensuring alignment with project goals. Options A, C, and D, while beneficial, do not provide the same level of ongoing interaction and timely feedback that sprint meetings facilitate.