PMI Agile Certified Practitioner (PMI-ACP) — Question 82

A member of the development team is working on a prioritized non-functional requirement involving integrating with a 3rd party system. This integration has not been done before on the project.
What should the project leader suggest?

Answer options

Correct answer: D

Explanation

The correct answer is D because developing and testing the implementation approach allows the team to validate the integration in a practical setting and gather feedback from stakeholders. Option A, while thorough, may lead to unnecessary overhead without practical testing first. Option B misunderstands the importance of non-functional requirements, which can be critical in integration scenarios. Option C risks delaying important integration work that could provide significant value to the project.