PMI Agile Certified Practitioner (PMI-ACP) — Question 80

The agile team disagrees with the business stakeholders on completing some epics.
What could help eliminate misunderstandings?

Answer options

Correct answer: A

Explanation

Reaching an agreement on requirements with all stakeholders ensures that everyone has a shared understanding of what is needed, minimizing misunderstandings. The other options do not directly address the core issue of aligning the team and stakeholders around the project's requirements.