PMI Agile Certified Practitioner (PMI-ACP) — Question 79

An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth.
What should the team do?

Answer options

Correct answer: B

Explanation

The correct answer is B because the team should prioritize their current iteration without getting sidetracked by external inquiries. This allows the project manager to handle the questions appropriately, ensuring that the agile process remains uninterrupted. The other options either disrupt the workflow or do not effectively address the situation at hand.