PMI Agile Certified Practitioner (PMI-ACP) — Question 74
During planning sessions, an agile practitioner notices that some team members do not share common ideas.
What should the agile practitioner do?
Answer options
- A. Ask the team if they would like to adopt alternative techniques
- B. Create a team norms document to set particular guidelines
- C. Ask the scrum master to resolve the issue at the stand up meeting
- D. Capture feedback during lessons learned at the end of the iteration
Correct answer: A
Explanation
The correct answer is A because suggesting alternative techniques can help the team find common ground and improve collaboration. Option B, while useful for setting guidelines, does not directly address the immediate issue of differing ideas. Option C places the responsibility on the scrum master instead of fostering team-driven solutions, and option D focuses on feedback after the iteration rather than addressing the current lack of shared ideas.