PMI Agile Certified Practitioner (PMI-ACP) — Question 75

The team is refining user stories during the backlog grooming session and confused on the acceptance criteria and level of details.
What should the agile practitioner do?

Answer options

Correct answer: C

Explanation

The correct answer is C because providing just enough detail in user stories encourages ongoing collaboration within the team. Option A is incorrect since test cases should be derived from user stories, not created beforehand. Option B is not suitable as overly detailed business requirements can hinder agile flexibility. Option D, while important, doesn't address the need for ongoing collaboration in crafting user stories.