PMI Agile Certified Practitioner (PMI-ACP) — Question 73
A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated.
What should the Scrum Master do?
Answer options
- A. Point out that the team chose to work on other requirements to speed up the project
- B. Ensure that the product owner reviews the contents of the information radiator
- C. Ensure that the next sprint planning meeting reviews the satisfaction histogram
- D. Point out that it is the responsibility of the product owner to clarify requirements
Correct answer: B
Explanation
The correct answer is B because the information radiator provides transparency about the current status of requirements and progress. This will allow the product owner to understand what has been completed and what remains. Options A, C, and D do not address the communication issue and do not facilitate the product owner's understanding of the project's current state.