A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated.
What should the Scrum Master do?

Answer options

Correct answer: B

Explanation

The correct answer is B because the information radiator provides transparency about the current status of requirements and progress. This will allow the product owner to understand what has been completed and what remains. Options A, C, and D do not address the communication issue and do not facilitate the product owner's understanding of the project's current state.