PMI Agile Certified Practitioner (PMI-ACP) — Question 66

A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.
What should the product owner do?

Answer options

Correct answer: C

Explanation

The correct answer is C because regular input from stakeholders ensures that the backlog reflects the most current priorities and needs of the project. Option A, while focusing on team collaboration, does not prioritize stakeholder feedback. Option B may overlook other important factors beyond just story points, and option D limits stakeholder interaction to a monthly basis, which may not be frequent enough for a fast-moving project.