PMI Agile Certified Practitioner (PMI-ACP) — Question 65
An agile team member identifies a potential problem within the project team.
How should the team's coach react?
Answer options
- A. Document the problem, escalate to the project manager, and develop a solution for the team
- B. Add the problem to the backlog and assign resolution to a future iteration
- C. Instruct the team to try to solve the problem within the team
- D. Perform root cause analysis and report the problem to the product owner
Correct answer: C
Explanation
The correct answer is C because it encourages team autonomy and collaboration in solving problems, which is a key aspect of agile methodologies. Options A and D involve external escalation, which can undermine the team's ability to self-manage. Option B delays the resolution and does not empower the team to address the issue immediately.